The schedule should be used as a way to force developers to do what they are told

2022-09-11 23
The schedule should be used as a way to force developers to do what they are told 0.00 из 5.00 0 оценок
Заказать работу

What are control mechanism? Please find F(alse) statement – Monitoring and Tracking are the same thing

What are metrics challenge? – All of the given

What are not the goal of establishing of project milestones: - Conduct the brainstorming of project design solution

What are NOT the key ideas behind a control mechanism for a software development project? –

Everything of the given is required

What are the inputs for Scheduling Process? – All of the given (WBS, OBS, Available Resources)

What are the matrics challenges? – All of the given

What are the maximum duration of the project in weeks and days at minimal quantity of engineers assigned (work week has 5 days)?

 

-

Weeks 3 days

What are the outputs for Scheduling Process? – All of the given

What assumptions would you have to make to estimate how many days it would take to deliver this project?

- All of the given

What do we use the Fishbone diagram for? – All of the given

What does EV metric measure? – Earned value – The measure of work performed expressed in terms of the budget authorized for that work.

What does PV metric measure? - Planned Value – The authorized budget assigned to scheduled work

What is an example of Cost metrics? – VAC

What is an example of Quality metrics? – Re-work

What is an example of Requirements metrics? – Traceability

What is an example of Scheduling metrics? – Number of Completion Activities

What is Benchmarking? – the continuous process of measuring products, services and practices against the toughest competitors or those companies recognized as industry leaders

What is meant by the term “project network diagram”? – Graphical representation of activities or nodes and the dependencies between them

What is needed to be developed for initial schedule process? – All of the given

What is not an example of Quality Assurance tools? – Planning Poker

What is NOT an input for Quality Assurance Process? – Change requests What is NOT an input for Quality Control Process? – Validated delivarables What is NOT an input of Quality Control Process? – Validated deliverables

What is NOT the metrics challenge? – Gain agreement on reporting and ongoing monitoring

What is the number of engineers you would need to assign to this project to deliver this project in the

 

 

minimum amount of time (work day has 8 hours)?                                                           You can assume that all the tasks are independent and all engineers who work on the tasks have basically the same skills but you can assign one task to one engineer – 5 engineers for 3 days

What is the number of engineers you would need to assign to this project to deliver this project in the minimum amount of time (work day has 8 hours)?


- 6 engineers for 2.5 days

When considering making the schedule for a project, which of the following items is critical to know: -

All of the given

Which one of the above risk areas must be done well on a project and why? – All areas

Which sequence is the correct to testing structure (organization)? – Unit test -> Functional Test -> Component Test -> Regression Test

While measuring the CV(Cost Variance) we will get the Negative value, what does it mean? – We have over planned cost

While measuring the SV(Schedule Variance) we will get the Negative value, what does it mean? –

Behind Schedule

While measuring the SV(schedule variance) we will get the Neutral value, what does it mean? – On schedule

While measuring the SV(schedule variance) we will get the Positive value, what does it mean? – Ahead of schedule

You are the only person working on this project and you are very skilled at the tasks. How long will it take you to complete the project if the estimates are accurate and you are not interrupted?

 - 18 days

PM 1701

1. List the set of tasks which if completed will get the project exactly 75% complete?

Task N 10 hours | Task O 5 hours | Task P 7 hours Task Q 4 hours | Task R 20 hours | Task S 12 hours Task T 19 hours | Task U 15 hours | Task V 8 hours

 

a. S, T, U, V


b. N, O, P, Q, R

c. N, Q, T, O, R, U, P

D. O, Q, R, T, U, S

2. If you have a work package consisting of the following tasks: A, B, C, D, E, F

And for each task, you do know the most likely, optimistic and pessimistic times to completion.

Using the PERT estimation technique calculate the estimated duration of the work package. A (T0=2, Tm=4, Tp=9)                         Predecessor: -

B (T0=5, Tm=8, Tp=14)        Predecessor: A C (T0=4, Tm=10, Tp=13)                     Predecessor: B D (T0=4, Tm=7, Tp=10)                       Predecessor: B

E (T0=11, Tm=14, Tp=20)  Predecessor: C, D F (T0=9, Tm=13, Tp=16)                     Predecessor: E

 

a. ~45.8

b. ~49.83

c. ~47.5

d. ~52

 

3. If the company you work for has a 5 day work week, how many weeks and days will it take to deliver the project?

Task A 2 days | Task B 3 days Task C 5 Days | Task D 2 days Task E 5 days | Task F 1 day

You can assume that all the tasks are independent and you have only one engineer who work on this project.

 

a. 4 weeks 2 days

B. 3 weeks 3 days

c. 2 weeks 4 days

d. 5 weeks 1 day

 

4. How many tasks do we need to complete to get to 50% or more complete?

Task N 10 hours | Task O 5 hours | Task P 7 hours Task Q 4 hours | Task R 20 hours | Task S 12 hours Task T 19 hours | Task U 15 hours | Task V 8 hours

 

A. N, O, P, R, V

b. N, Q, T, V

c. N, O, P, Q, R

d. S, T, U

 

5. Most issues/problems require more than one measurement to characterize and understand. Is this sentence True or False?

 

A. True

b. False

 

6. While measuring the SV(schedule variance) we will get the Neutral value, what does it mean?

 

a. On schedule

b. Behind Schedule

C. Ahead of Schedule

d. None of the given

 

7. What is Benchmarking?



Поделиться с друзьями:

Особенности сооружения опор в сложных условиях: Сооружение ВЛ в районах с суровыми климатическими и тяжелыми геологическими условиями...

Механическое удерживание земляных масс: Механическое удерживание земляных масс на склоне обеспечивают контрфорсными сооружениями различных конструкций...

Эмиссия газов от очистных сооружений канализации: В последние годы внимание мирового сообщества сосредоточено на экологических проблемах...

История развития пистолетов-пулеметов: Предпосылкой для возникновения пистолетов-пулеметов послужила давняя тенденция тяготения винтовок...



© cyberpedia.su 2017-2024 - Не является автором материалов. Исключительное право сохранено за автором текста.
Если вы не хотите, чтобы данный материал был у нас на сайте, перейдите по ссылке: Нарушение авторских прав. Мы поможем в написании вашей работы!

0.011 с.