KOBE EARTHQUAKE – assessing the damage — КиберПедия 

Индивидуальные и групповые автопоилки: для животных. Схемы и конструкции...

Организация стока поверхностных вод: Наибольшее количество влаги на земном шаре испаряется с поверхности морей и океанов (88‰)...

KOBE EARTHQUAKE – assessing the damage

2017-07-01 216
KOBE EARTHQUAKE – assessing the damage 0.00 из 5.00 0 оценок
Заказать работу

Over 2000 dead, including many port workers, and thou­sands more homeless. The damage sustained by the Port of Kobe, Japan’s premier port, in the earthquake disaster of 17 January has been estimated at JY940 bill or almost US$ 1 bill. Kobe port accounted for almost one fifth of all the di­rect and dependent jobs in the city, and the port and related industries represent almost 40 per cent of all earnings.

The earthquake had a Richter magnitude of 7.2.The seismic cen­tre was very close to Kobe and oc­curred close to the surface. All the container berths under the control of Kobe Port Terminal Corpora­tion (KPDC) on the man-made Rokko and Port Islands were put out of action, with sunken and flooded apron areas.

Only 30 of the 150 public berths managed by Kobe Port Au­thority could be used and just 39 of the 89 public warehouses and transit sheds were in service, to a limited extent. The Kobe Ohashi Bridge supports collapsed and the joints were damaged. It will take 2-2.5 years to restore the bridge completely and fully reopen both upper and lower level roadways.

The Maya Ohashi bridge is in­tact but major inspection work must be carried out before it can be reopened. Complete restoration of the Harbour Highway will take 2-3 years and work will be done in three phases (No 2 eastern indus­trial area to Takaha; Takaha to Maya; and Maya to Shinko No 4 Pier).

The joints of the Rokko Ohashi Bridge supports were damaged, but emergency works have been completed. There is limited access on both the upper and lower levels and complete res­toration is anticipated within 9-12 months. Early estimates indi­cate that two years will be required to rebuild the elevated expressway which is die main artery connect­ing the port with Osaka and To­kyo and the only one really suit­able for container trucks.

 

Relief supplies

Liquefaction caused fill to settle. Sand and water erupted and splashed

against the top of this 9ft high container. (Source: Ibid)

The bridges and various quays (Hyogo No 3, Shinko No 8 east, Maya No 1) were cleared to receive emergency supplies within days of the disaster. The immedi­ate goal is to recommission the lesser-dam aged berths within six months and restore the city and port fully within 2-3 years. Gen­erally speaking the facilities on Rokko Island sustained less dam­age than those on the earlier Port Island or the Maya Terminal (the infilled Maya Piers on the main­land converted to a common user container terminal). Rokko was provided with better sand stabilisation than Port Island and therefore sustained less liquefac­tion damage.

According to a report by Liftech Consultants Inc, which was hired by APL to assess dam­age to its terminal on Port Island, the entire interior of Fort Island settled due to liquefaction of the underlying fill. The failure of the caisson wall foundation appears to be due to pressure from the liq­uefaction of the fill material be­hind the caisson and lateral seis­mic forces. Pending further inves­tigations, adds Liftech, it is not clear whether the caissons rotated due to stress failure in, or lique­faction of, the underlying fill.

Road to recovery

According to the port, almost 60 public berths have become avail­able again for conventional traffic and 14 berths for passenger traf­fic. Maya No 1 berth will be avail­able for containerships at the end of March, says the port, along with seven of die KPDC berths, albeit each with just one crane. These are Port Island 2 (UASC/ Nedlloyd), 4 (both 3 and 4 were empty as NYK had just transferred completely to Rokko) and 7 and Rokko Island 1 and 2 (Sealand), 4 (Maersk) and 7 (NYK).

KPDC aims to get all its berths operating on a temporary basis with one crane each within three months and recommission the remaining cranes at 6-monthly intervals. It is understood that all the cranes will be taken back to the manufacturers' plants and fit­ted with new frames.

Traffic diverted

 

As the caisson moved out so did the waterside rail and caused the crane to spread.

On this berth one crane collapsed and the others buckled.

 

In the first few days following the earthquake, container traffic was diverted mainly to Tokyo (32 per cent),Yokohama (30 per cent) and nearby Osaka (25 p.er cent) which also sustained some minor dam­age in the quake. Containers were also diverted to Nagoya and Shimizu and die principal Korean containerport, Pusan.

If lines co-operate with each other and working practices are adjusted there should be sufficient capacity in Tokyo Bay, Osaka and Nagoya to absorb the diversion, although transhipment traffic could well be switched to ports such as Hong Kong, Kaohsiung or Pusan, particularly given the high handling charges in Japan. Some lines resumed Kobe calls within a remarkably short time (eg APL is making weekly calls with a self-sustaining vessel).

 

All askew

Altogether there are 46 container cranes in Kobe - 39 on Port Is­land and Rokko Island and seven at the Maya Terminal. The cranes at Berth C9 on Port Island (used by MOL) were inclined while the four cranes at the Sealand termi­nal on Rokko (RC1 and 2) were all off the rails and inclined about 20 deg to the water. At RC3 (K-Line) one gantry crane had report­edly collapsed into the sea and an­other collapsed onto the apron.

The cranes at the Maersk and NYK terminals (RC4-5 and RC6-7) were all inclined. There was also crane damage sustained at the Maya terminal on the main­land and in many instances the ground level had sunk on the aprons and in the CYs behind them. One container quay crane was damaged at Nanko Terminal in Osaka and the C6, C7 and C9 common user container berths were out of action for a short period. But Osaka city and pore es­caped lightly compared to Kobe.

Construction report

According to the initial on-the-spot report from Liftech’s Feroze Vazifdar accompanied by a geotechnical engineer from Harza, Peter Kaldveer, the berths at Kobe are contained within pe­rimeter quay walls and filled with reclaimed granular fill material hydraulically placed over natural sea bottom clay. The walls are made from 10m wide x 13m deep hol­low concrete caissons filled with granular material. Girders for the waterside crane rails are placed over the caisson wall. The caissons were designed for a lateral coeffi­cient of 0.lg while a seismic co­efficient of 0.2g was usually speci­fied for the container cranes.

 
 

31.85 After

Graphical cross-section summary of Kobe port construction, with 50ft and 100ft gauge

crane rails, and earthquake consequences (Source Liftech Consultants)

 

A lateral force of 0.1g is lower than would normally be specified today in earthquake zones. The Pier J expansion area at Long Beach, for example, is designed to 0.2g while the structures will re­spond to a force of 0.33g. The wharf structure uses the so-called “structural fuse” design developed by Dames & Moore in conjunc­tion with the port’s engineers.

The main seismic event at Kobe had a duration of 20 sec­onds and produced peak effective lateral accelerations near the port of 0.8g (north-south) and 0.6g (east-west) while peak vertical ac­celeration was 0.3g.

Unwelcome settlers

The caissons at Port Island and Maya terminal have settled be­tween 0.7m and 3m and rotated up to 3 deg, says Liftech, which has caused the crane rails to spread. The tops of the waterside rail gird­ers are submerged in places and the fill adjacent to the caissons has dropped an additional 2-3m.

The cranes with a 50ft gauge have their landside rail girders sup­ported on steel piles. These have not settled appreciably but have rotated 3-5 deg in places. The cranes with a 100ft gauge have their landside rail girders on grade beams over engineered fill and these have settled in places. The crane rail girders have spread 1-2m at Port Island and 4-5m at Rokko Island.

Crane damage varies at differ­ent locations. A large number have significant structural damage and could collapse in the event of a strong aftershock. According to Liftech, the damage to the cranes is primarily due to the rails spread­ing and settling.

That is, it is as if the cranes were trying to “do the splits” as the quays separated and they are buckled at the portal ties. Liftech recommends that cranes are built with movement and rotation re­sistant ductile frames with heavy portal ties.The three MHI cranes at the APL terminal on Port Is­land (PC 5) were designed by Liftech and reportedly stood up well to the earthquake.

Liftech adds, however, that if the Guam earthquake of 1993 is anything to go by, it will take several months for the ground to solidify. This could cause further problems in the event of aftershocks.

 

The pile-supported dock structure performed well, while the caissons settled and rotated out.

Liquefaction caused the fill within the settled caissons to settle about 3ft.

Avoid catastrophe

Another firm of structural engi­neers, Casper, Phillips & Associ­ates (CP&A), reports that a crane designed to meet its catastrophic load condition is able to resist the largest earthquake. A heavier and hence more costly steel structure is required but, says CP&A, when owners are asked if this is a price they are willing to pay for added protection, they usually accept it.

Having said this, the massive Kobe reconstruction project will be a fantastic consumer of steel. Steel prices seem set to rise sharply. This is bound to impact on the cost of large steel struc­tures such as cranes and the dif­ferential between a light and a heavy crane is going to widen.

When a crane is not tied down, says CP&A, the earthquake loads are limited to the load needed to tip the crane onto two legs. Once the crane starts to lift, says Bill Casper, the load cannot increase further because the addi­tional seismic energy is absorbed by the raising of the crane’s cen­tre of gravity.

The crane cannot tip over be­cause a fraction of a second later the load reverses. Earthquake tip­ping load is between 50 and 100 per cent of the crane weight de­pending on railspan and crane height. When the crane tips onto two legs they have to support the entire weight of the crane; other­wise the crane collapses and falls to the ground.

If the crane has been tied down, continues CP&A, there is no limit to the earthquake load­ing except that it will peak when the structure is absorbing energy as fast as seismic energy impinges on it. In a large earthquake this happens when parts of the steel structure are being plastically bent back and forth.

Earthquake forces increase in proportion to the strength of the crane, up to the severity limit of the earthquake itself. If the earth­quake is strong enough to bend all four legs, the crane is likely to collapse to the ground.

From the point of view of earthquake protection, then, tying down the crane is the worst thing to do. The situation is exactly analo­gous to the concept of “seismic iso­lation” for buildings.

Exactly one year to the day be­fore the Kobe disaster, on 17 Janu­ary 1994, a 6.7 Richter scale earth­quake severely damaged 31 Los Angeles area hospitals but the USC University Hospital, the world’s first “seismically isolated” building, rode out the earthquake with no dam­age at all.

Similarly, in the Kobe quake, the 6-storey West Japan Computer Center located 20 miles west of the city cen­tre and one of the world’s largest seismically isolated structures (ie the equivalent of a crane free to lift on the rails), suffered no damage at all. The peak force accelerations at the roof were lower by a factor of up to 9 (ie 0.07g-0.01g compared to 0.67g-0.97g) than those of a similar-sized but conventional fixed base building (equivalent to a tied crane).

 

Earthquake protection for cranes and quays will be ad­dressed at TOC Asia in Sin­gapore in April by Bill Casper of Casper, Phillips & Associ­ates (CP&A) and Liftech Consultants’ Mike Jordan. CP&A has a specific crane design to cater for catastrophic loads while Liftech, whose crane designs include the Mitsubishi-built post-Panamax cranes at APL’s terminal in Kobe, was appointed by the carrier to assess the damage to its facilities in the port. Shunichi Yano, managing director of NYK Singapore Pte will also address the long term implications of the Kobe disaster at TOC Asia. NYK’s new facility on Rokko opened only last year.

 

 

REFERENCES

 

Cargo systems, January 2004

Cargo systems, June 2004

Cargo systems, August 2004

Cargo systems, September 2004

Cargo systems, October 2004

Cargo systems, January/February 2005

Cargo systems, April 2005

Cargo systems, June 2005

Cargo systems, July/August 2005

Cargo systems, September 2005

Cargo systems, November 2005

WorldCargo news, February 1995

WorldCargo news, October 1995

WorldCargo news, June 1997

WorldCargo news, July 1997

WorldCargo news, August 1997

WorldCargo news, January 1998

WorldCargo news, August 2003

WorldCargo news, August 2004

WorldCargo news, November 2004

WorldCargo news, January 2005

WorldCargo news, February 2005

WorldCargo news, May 2005

WorldCargo news, June 2005

WorldCargo news, July 2005

WorldCargo news, August 2005

WorldCargo news,October 2005

International Tanker Owners Pollution Federation, Seaways, October, 2007

Seaspeak Training Manual. – Oxford: Pergamon Press, 1989. – 298 p.

IMO Resolution A.918(22). IMO standard marine communication phrases. London, 2001. – 104 p.

Стандартные фразы ИМО для общения на море. – СПб.:ЗАО ЦНИИМФ, 1997. – 476 с. («Судовладельцам и капитанам», вып. 9).

Фаворов П. А. Англо-русский морской технический словарь. – М.: Воениздат, 1977. – 931 с.

Яковлев А. А., Яковлев В. А. Основы морской технической терминологии. – Одесса: Моряк, 1977. – 100 с.

Апресян Ю. Д., Медникова Э. М., Петрова А. В. и др. Новый большой англо – русский словарь. В 3 т. Под общ. рук. Апресяна Ю. Д., Медниковой Э. М. – М.: Рус. яз., 1998. – 832 с.

 

 

CONTENTS

UNIT 1 – Cranes – part 1…………………………………………………… 3

– part 2……………………………………………...............7

– part 3…………………………………………………….12

– part 4…………………………………………………….15

– part 5…………………………………………………….18

– part 6…………………………………………………….20

– part 7…………………………………………………….22

– part 8…………………………………………………….25

– part 9…………………………………………………….28

– part 10…………………………………………………...32

– test……………………………………………………….35

UNIT 2 – Straddle carriers – part 1………………………………………….39

– part 2………………………………………….42

– part 3………………………………………….45

– part 4………………………………………….48

– test…………………………………………….50

UNIT 3 – Reach stackers – part 1……………………………………………53

– part 2…………………………………………….56

– part 3…………………………………………….59

– part 4…………………………………………….61

– part 5…………………………………………….64

– test……………………………………………….67

UNIT 4 – Tractors and other machines – part 1………………………............71

– part 2……………………………...74

– part 3………………………….......77

– part 4……………………………...79

– part 5……………………………...82

– test………………………………...85

UNIT 5 – Car carriers – part 1………………………………………………..88

– part 2…………………………………………….......91

– part 3…………………………………………...........95

– test………………………………………..................97

UNIT 6 – Forest products handling machines – part 1……………….............99

– part 2……………………...102

– part 3………………...........105

– part 4………………...........107

– part 5………………...........109

– test…………………...........111

UNIT 7 – Ports: environment and nature – part 1………………………......114

– part 2.A………………..............117

– part 2.B…………………..........119

– part 2.C………………..............122

– part 3………………..................124

– test……………………..............127

UNIT 8 – Ports of Russia……………………………………………............130

UNIT 9 – Ports of the world……………………………………...................135

UNIT 10 – Kobe earthquake – assessing the damage……………….............142

KEYS……………………………………………………………...................147

REFERENCES………………………………………….................................151

 

 

Позиция №

в плане издания

учебной литературы

МГУ на 2009 г.

 

 

Субботина Галина Николаевна,

доцент кафедры английской филологии

Субботин Михаил Владиславович,

капитан дальнего плавания

 

PORT CARGO HANDLING MACHINERY

 

Учебное пособие

 

________________________________________________________________________________

9,6 уч.-изд. л. Формат 60 × 84/16

Тираж 100 экз. Заказ №_________

Отпечатано в типографии ИПК МГУ имени адмирала Г. И. Невельского

690059, г. Владивосток, ул. Верхнепортовая, 50а


Поделиться с друзьями:

Адаптации растений и животных к жизни в горах: Большое значение для жизни организмов в горах имеют степень расчленения, крутизна и экспозиционные различия склонов...

Общие условия выбора системы дренажа: Система дренажа выбирается в зависимости от характера защищаемого...

Автоматическое растормаживание колес: Тормозные устройства колес предназначены для уменьше­ния длины пробега и улучшения маневрирования ВС при...

Своеобразие русской архитектуры: Основной материал – дерево – быстрота постройки, но недолговечность и необходимость деления...



© cyberpedia.su 2017-2024 - Не является автором материалов. Исключительное право сохранено за автором текста.
Если вы не хотите, чтобы данный материал был у нас на сайте, перейдите по ссылке: Нарушение авторских прав. Мы поможем в написании вашей работы!

0.071 с.